Councillor’s concern over tourism and heritage in Antrim as it emerges Steeple House works may not be complete until 2030

Steeple House before the 2019 arson attackplaceholder image
Steeple House before the 2019 arson attack

A SINN Fein councillor has expressed concern over staffing and the wider tourism and heritage experience, particularly in Antrim, as reps were given an update on major capital projects in the borough.

The comments were minuted in an ‘in confidence’ sitting of the May meeting of Antrim and Newtownabbey Borough Council, where reps were told that work on Steeple House and parklands may not be complete until 2030, 11 years after a devastating fire in 2019.

At a corporate workshop in November 2025, there was an updated on the entirety of the capital programme, the progress of specific projects and the ongoing review of project business cases.

Specific reviews were brought to members and the relevant committee for their consideration and the capital programme updated accordingly.

The draft capital program for both the short and medium term (2026-2031) covering the remainder of the current term of council and the next 2027-2031 council term was presented.

A ‘comprehensive, evidence-based review’ of Council’s Capital Development Section was also progressed by The Strategic Investment Board, evaluating its current organisational structure, roles, and responsibilities, end-to-end capital programme management processes from inception to completion and the relationship and management of internal stakeholders, including the ‘Senior Responsible Officer and Project Sponsor’.

It looked at the relationship and management of external services, including the ‘Project Manager and Designer’ and contractors, capacity, capability, and resource allocation and governance, risk management, and compliance frameworks.

Also considered were ‘strategic alignment with corporate objectives and statutory obligations and performance in delivering capital projects’.

The review identified strengths, weaknesses, and opportunities for improvement, ‘ensuring the section was positioned to deliver the capital programme efficiently, in accordance with client departmental needs, and in line with public sector best practice’.

The report also looked at affordability, and the annual capital provision for ongoing fleet, ICT hardware and lifecycle replacement costs were also included.

Members were apparently ‘made aware of the factors impacting on project delivery and prioritisation, for example, availability of funding, land availability, external funder deadlines, supply and demand analysis, affordability, the limited resources of the capital team and planning constraints’.

“These were all factors to consider in the review of future projects and the priority for their delivery.” said the report, ominously continuing: “It was also expected that new additional projects will be conceived over the next five years as a result of the factors above and indeed some of the projects listed may not proceed as circumstances and demands change.”

Reps were updated on capital projects programmed to commence in the 2026/27 financial year, along with the estimated project budget, anticipated funding and corresponding rate impact.

Funding also included contributions from reserves, like the capital receipts reserve, or ongoing revenue savings as well as grant income. These projects were largely well advanced in terms of Outline Business Case, planning approval and consultant or contractor.

There will be a new audio visual system and solar panels at the council HQ at Mossley Mill.

All cost were redacted and most were outside the Antrim, Dunsilly and Airoport electoral areas, although it was noted that Muckamore Cricket Club works on a fence and car park would be complete by this November, while the conversion of the gift shop at Clotworthy House to an ice cream parlour will be complete by April 2028.

Antrim Forum hockey pitch floodlight replacements will be complete by July 2027.

A second list concerned capital projects programmed to commence in the 2027/28 financial year, along with the estimated project budget and anticipated funding. These projects are largely well advanced in terms of Outline Business Case.

Antrim Skate Park is slated to be complete by April 2028. The theatre at Mossley Mill is set for new lighting.

The Cranfield Slipway project looks set to be complete by March 2028.

However most projects were again outside the legacy Antrim Borough area.

Capital projects programmed to commence in the 2028/29 and 2029/30 financial years, along with the estimated project budget and anticipated funding, were also listed.

It was noted that these schemes were ‘less certain in terms of budget, timeline and funding’.

They included the Crumlin Public Realm scheme, with a completion date of June 2029, with the reinstatement and development of Steeple House, outbuildings and parkland given a completion date of October 2030 - which will be 11 years after the former council HQ burned down in 2019.

A refurbishment of the Castle Gardens Café has been given a completion date in 2031.

In summary, the capital programme totalled an estimated £56.9m over the remaining term and the next term of council, with anticipated external funding of £18.9m.

The rate impact of these schemes was estimated to be an additional cumulative increase of 4.31% An increase in costs was said to be: “Largely mitigated by the reduction of loan principal and interest through the expiration of loans within the councils current loans portfolio over the same period.”

The current long term loan position and the corresponding future position, assuming no new loan borrowing was shown to the meeting.

The report said: “The rate impact of the reduction in loan repayments over the same period was estimated to be a cumulative decrease of 2.49%. i.e. a net increase in rates due to the capital programme of 1.82% over 5 years.

“Members sought clarification on several of the Capital Projects tabled above.

“It was agreed that a number of matters be progressed including: an expression of interest in relation to land for a new household recycling centre in Crumlin, public access for boat launches at Lough Neagh, an intermediate pitch in Glengormley and a further report to June Operations Committee on pitch provision.”

The minutes said: “(Sinn Fein Antrim Town) Councillor (Lucille) O’Hagan’s concerns regarding staffing and the wider tourism and heritage experience particularly in Antrim were noted.

“The Chief Executive confirmed that further clarification on specific issues raised would be provided directly to her.”

It was moved by UUP Councillor Robert Foster and seconded by his party colleague Alderman Mark Cosgrove and resolved that the short-term and medium-term Capital Project programme, to allow the prioritisation of projects (dependent on the impacting factors) be approved.

The minutes concluded: “Members noted that the Capital Programme was subject to annual review by elected members, the approval did not preclude additional projects being included in the programme, subject to members' agreement, and the approval would not negate the requirement for the application of the business case process to assess need/demand, viability, affordability and sustainability of the projects.”