Extension planned for Antrim Primary School

placeholder image

PLANS to extend Antrim Primary School have been included in a list of major planning proposals coming before Antrim and Newtownabbey Borough Council. Prospective applicants for all development proposals which fall into the ‘major development’ category are required to give at least 12 weeks’ notice to the Antrim and Newtownabbey Council that an application for planning permission is to be submitted.

PLANS to extend Antrim Primary School have been included in a list of major planning proposals coming before Antrim and Newtownabbey Borough Council.

Prospective applicants for all development proposals which fall into the ‘major development’ category are required to give at least 12 weeks’ notice to the Antrim and Newtownabbey Council that an application for planning permission is to be submitted.

This is referred to as a Proposal of Application Notice (PAN).

Three PANs were registered during July 2023, a meeting of the council’s Planning Committee is due to hear this week.

The first is for a mixed use development comprising Class B business uses and sui-generis uses at The Auction Yard on

Moira Road in Crumlin

The second is an extension to Fairview Primary School in Ballyclare and other ancillary/associated works, the third is for an extension to the existing school and other ancillary/associated at Antrim Primary School.

The prospective developer must consult the community in advance of submitting a major development planning application.

Following the 12-week period an application, accompanied by a pre-application community consultation report, outlining the consultation that has been undertaken regarding the application and detailing how this has influenced the proposal submitted.

Meanwhile, two appeals were dismissed during July 2023 by the Planning Appeals Commission (PAC).

One was in relation to a proposed replacement garage at Abbey View, in Muckamore and another was for the erection of single story replacement agricultural style shed to west of site and new replacement timber fencing to front of site at Doagh Road in Ballyclare.

Monday night’s meeting was also due to hear about the annual Northern Ireland Planning Statistics 2022/23 Statistical Bulletin produced by the Analysis, Statistics and Research Branch of the Department for Infrastructure (DfI).

The figures show that during 2022/23 a total of 732 new applications were received by the council, a decrease of 175 from the previous year.

A report said that whilst this pattern of decrease was also experienced by all Councils in Northern Ireland, Antrim and Newtownabbey Borough Council were the fourth ranked Council to experience the least decreased of new applications.

Figures show that from April 2022 to March 2023 the Council processed 16 major planning applications, a 100 percent increase in comparison to the previous year.

Across all Planning Authorities in NI the average processing time for major applications during 2022/23 was 57.8 weeks, the council performance exceeded this, achieving an average processing time of 52.1 weeks.

Average processing time for local applications during 2022/23 was 19 weeks, the council performance exceeded this achieving an average processing time of 13.4 weeks.

The council was one of only three to achieve the statutory target of 15 weeks during 2022/2023.

DfI figures indicate that the council opened 332 enforcement case during 2022/23 and closed 360 closed.

The report said: “The council is continuing to reduce the proportion of our live enforcement cases that have been ongoing for over 2 years, this is currently sitting at 14% in comparison to almost 16% at 31 March 2022.”

The council also has the lowest proportion of cases over two year old across all planning authorities.

Also on the agenda was the news that the Permanent Secretary for the Department for Infrastructure, Dr Julie Harrison, ‘has written to all councils with an update on the Planning Improvement Programme (PIP) and has emphasised the important role all councils have to play in this process’.

The report said that officers are currently preparing a draft Antrim and Newtownabbey Planning Improvement Programme for consideration, which will incorporate areas identified at the local level alongside the Strategic PIP with central government.

As part of the Strategic PIP, it been proposed that the council will lead an event with statutory consultees in relation to improving the Local Development Plan process in order to assist in the implementation and delivery of the Strategic PIP

Members were also due to be reminded that a report was presented to Planning Committee regarding the Guide on Planning Fraud Risks published by the Northern Ireland Audit Office in March 2023.

The report said: “Following a review by the Planning and Internal Audit teams and in line with the guidance provided by the NIAO it is roposed that a self-assessment form be

completed by all those in the Council who are involved in any way in the planning process.

“This will provide the baseline understanding of the level of awareness of the controls that are in place across the planning process and enable the development of an appropriate training and communication plan to ensure the council’s risk in relation to planning fraud continues to be adequately mitigated.

“It is proposed that the self-assessment form will be issued to all members of the Planning Committee by the end of August with a return date stated.”