Holywell Hospital conditions are 'intolerable and unacceptable'


THE issue of Antrim’s delayed new mental health hospital will be raised with the Permanent Secretary for Health at a meeting this week. The news was revealed at the latest meeting of the Northern Health and Social Care Trust’s Board, where the Chair branded working conditions at Holywell Hospital as ‘intolerable and unacceptable’.
THE issue of Antrim’s delayed new mental health hospital will be raised with the Permanent Secretary for Health at a meeting this week.
The news was revealed at the latest meeting of the Northern Health and Social Care Trust’s Board, where the Chair branded working conditions at Holywell Hospital as ‘intolerable and unacceptable’.
The new Birch Hill Centre for Mental Health has been designed to replace the crumbling listed building.
The Trust’s outline business case for a new 134 bed Mental Health Inpatient Service on the Antrim Area Hospital site was approved in 2020.
The ten-year plan for capital investment includes reconfiguring the site to include mental health services.
But in March, it was announced that the next stage of the vital new project had been ‘paused’ due to funding issues.
The Department of Health has since said that all future capital projects are under review, due to budget constraints.
Birch Hill is set to accommodate eight wards, including Adult Acute, Psychiatric Intensive Care, Dementia and Addictions.
Dr Petra Corr, the Northern Trust’s Director of Mental Health, Learning Disability and Community Wellbeing, told the meeting that the Trust had presented its ‘line of vision’ to the Department of Health in May, but that there was still no capital funding available to proceed to Stage 4 of the project.
She thanked Health Minister Mike Nesbitt for his visit to Holywell, which houses 400 staff as well as patients, and for looking at the Birch Hill plans, saying he was ‘very positive’ about the scheme.
Also thanked was South Antrim MLA Robin Swann, for raising the ‘critical need’ for the facility in the House of Commons, as covered by the Antrim Guardian.
Dr Corr also noted that the design team behind the new hospital had recently been runners-up and ‘Highly Commended’ in a recent UK awards scheme.
She said that further delays were causing worries as regards the safety of patients and staff and the costs involved in maintaining Holywell, which she said was ‘significantly ageing and a cause of concern for us’.
As well as the original 1898 asylum buildings, built to accommodate 1000 patients, and the sprawling estate and grounds, extra wards have been added to Holywell over the years, and it now offers 116 acute in-patient beds.
Anne O’Reilly, chair of the Trust Board, said that Birch Hill would be brought before a Trust meeting with the Permanent Secretary this week and added: “We are carrying all of the risks, from vulnerable service users to staff.”
“When the Minister visited, he saw first hand some of the conditions they are working under, which are intolerable and unacceptable.”
Ms O’Reilly added: “It is high on our agenda as a Trust board to seek a decision. We need to know what is going on.”
A paper presented to the Board said that a new build will reduce the ligature related issues and incidents of violence and aggression to a rating of 12 on the Trust Risk Register. Holywell is currently not compliant and has a high rating of 20.
A new build may also reduce the current inability to secure acute psychiatric beds to a rating of 12 on Trust Risk Register. Again, Holywell is not compliant at present, with a high rating of 25.
The total business case cost including fees, inflation and ‘Optimism bias’ is now approximately £155m.
The paper said: “The major risk continues to be the ongoing Department of Health review of Capital Projects across all Trusts will extend the programme and the associated costs.
“Should the review lead to a delay in the project, the Trust will continue to carry the risks associated with Holywell Hospital which will increase as will the associated costs of maintaining the building.”
Projects including archaeology and the mound car park are being developed to tender package stage.
The work for the planning application for the junction at Bush Road and the new access road was reviewed and approved by the Trust on Friday 6 June 2025.
The paper said: “All of these projects are required to ensure a cleared site for both the new access route and for the construction of the main Birch Hill Project. These enabling works elements cannot commence without funding approval. In order to de-risk the main project it would be beneficial to continue to advance these works.
“Any delay to these works will only increase their cost to complete.
“The Trust are developing responses to final set of queries on the Mental Health Inpatient Addendum received on 8th May 2025.
“Support is being provided by the Health Estate Project Manager and Quantity Surveyor. It is proposed that they could be completed by the end of June/early July 2025.
“The Trust continue to await the outcome of the Strategic Investment Committee, as this may have an impact on time, cost and scope, before a resubmission to the Department of Health.
“Approval of the Addendum is required to secure funding to commence RIBA Stage 4 and the completion of Enabling Works for progression to tender in advance of the Full Business Case.”