No new jetty for Cranfield

placeholder image

THE scheme to replace Cranfield Jetty will be downscaled due to ‘increases to costs, the constraints of affordability and the requirement for prioritisation’, it’s been revealed. The news was delivered behind closed doors at an ‘in confidence’ session of the Community Development Committee meeting in February.

THE scheme to replace Cranfield Jetty will be downscaled due to ‘increases to costs, the constraints of affordability and the requirement for prioritisation’, it’s been revealed.

The news was delivered behind closed doors at an ‘in confidence’ session of the Community Development Committee meeting in February.

A report said: “Cranfield, located on the Northern shore of Lough Neagh, is a picturesque hamlet containing the ruins of a 13th century church and graveyard, and a holy well said to have been blessed by St Olcan who himself had been baptised by St Patrick.

“The Church and Holy Well are maintained by the Department for Communities’ Historic Environment Division, while the car park, toilet block and wider site is the responsibility of the council.

“For many years a small slipway and jetty allowed public access to Lough Neagh from the site, but these were closed in 2019 and the jetty subsequently demolished following a structural survey that identified significant deterioration and serious health and safety concerns.

“The site of the slipway and jetty was leased from the Shaftesbury Estate on a rolling basis with an annual fee, and any development works require formal landlord consent alongside statutory planning approvals.

“Officers engaged with the Shaftesbury Estate about any council decision regarding the slipway and jetty.”

At the Council meeting in January 2021, the replacement of the jetty and slipway was approved at a redacted cost.

At the Council meeting in September 2021, it was agreed that a business case for the reinstatement of the jetty be developed.

At the Community Planning Committee in December 2022, it was approved to replace the concrete slipway, refurbish part of the jetty and install a floating pontoon a little further out from the shoreline linked to the refurbished jetty with a galvanised walkway.

At the Community Planning Committee in February 2024, it was agreed to continue with the approved approach but with a shorter jetty and/or pontoon to enable smaller boats to moor.

The cost of this option including fees and contingency was redacted.

At the May 2024 Policy and Governance Committee, Members were advised that, ‘based upon inflationary increases to costs, the constraints of affordability and the requirement for prioritisation’, a review of the Capital Programme and Capital Project Management Process had commenced for members’ future consideration.

The minutes said: “As a result of this, the Strategic Investment Board were commissioned to review a range of capital project business cases which included the Outline Business Case for Cranfield Jetty.

“At the Council meeting in January 2026 an update on the Council’s Capital programme was noted.”

Having completed a review of the options for the development of Cranfield Jetty, SIB had completed an updated Outline Business Case for this project which was circulated for members’ information.

“The Outline Business Case considered the evidence of need and the options for the development of Cranfield Jetty and the associated capital and recurring revenue costs.

“Cranfield’s rural setting with no accessible amenities, road infrastructure access constraints as well as recurring blue/green algae naturally capped both the intensity and seasonality of use.

“In addition, full marina facilities existed in close proximity at both Ballyronan and Antrim Loughshore Park well serviced by a range of amenities for overnight mooring and slightly further away Kinnego Marina, at Oxford Island provided similar high-quality facilities for access to Lough Neagh with all three facilities supported by caravan parks.

“The Business Case identified the preferred option for Cranfield Jetty Capital Project as complete removal of the existing jetty, refurbishment and extension of existing slipway to 8m x 20m at an estimated cost of (redacted) and an annual revenue consequence of (redacted).

“This option provided a safe, durable, and sustainable solution that directly addressed current health-and-safety risks, restored community access to Lough Neagh at Cranfield, and delivered social and well-being benefits within available resources.”

The estimated capital cost of the preferred option was redacted, as were the annual loan costs of over the estimated 15 years life span of the project and annual revenue maintenance costs.

The minutes continued: “Approval of the Stage 1 Outline Business Case for the Cranfield Jetty would progress the project to Stage 2 of the Council’s Capital Programme which would involve appointment of an Integrated Consultancy Team (ICT) and preparation of a full business case including planning and procurement.

“The full Business Case would be brought back to a future meeting of the committee seeking the investment decision allowing the appointment of the winning tenderer, contract management and construction.

“In response to questions from members, the Director of Community and Culture provided clarification on the financial status and confirmed that there would be elements of Our Historic Borough delivered in the Cranfield area.

“She also advised that consultation had not been carried out yet as the project was only at Stage 1 of the process. She also responded to a member’s query regarding jet ski use.”