'Review' taking place as costs for new mental health development soar

placeholder image

THE Department of Health has released a worrying statement on the future of a new £143m mental health facility in Antrim. On the front page of the Antrim Guardian this week, we reported on how, at a meeting of the Northern Health and Social Care Trust board last week, members were told that plans for the Birch Hill scheme have been delayed again.

THE Department of Health has released a worrying statement on the future of a new £143m mental health facility in Antrim.

On the front page of the Antrim Guardian this week, we reported on how, at a meeting of the Northern Health and Social Care Trust board last week, members were told that plans for the Birch Hill scheme have been delayed again.

Planning permission for the modern 134-bed complex at Bush Road was approved by Antrim and Newtownabbey Borough Council last summer, with estimated completion by late 2028.

Trust Chiefs had reached the end of the third stage of the plan, with a view to receiving the building for commission on 31 December 2029 - already a delay.

But Dr Petra Corr, divisional director of mental health, learning disability and community well-being, revealed last week that the Trust does not have the funding ‘at this point in time’ to continue on to stage four.

The facility is required in order to replace Holywell Hospital, an old ‘asylum’ built in 1898, which currently has just over 100 inpatient beds.

The meeting also heard that there are currently no plans yet for future use of the listed building, which still houses hundreds of staff.

Dr Corr said that while she couldn’t offer any assurances on the project last week, that it faced ‘vulnerability’ and that finances were in a ‘challenging position’, that the plans had not been formally paused.

However in a statement to the Guardian from the Department of Health, which we recieved after our deadline on Monday evening, a spokesperson said that the Outline Business Case for the new Mental Health Unit in the Northern Trust, known as Birch Hill, received Department of Health approval in August 2020.

“The estimated capital cost at that stage was £88 million. Due to financial constraints, the Department could not allow the project to immediately proceed in its entirety but was able to provide approval for the initial Design Stage, estimated at £4.1 million.

“Following the completion of this initial design phase, the capital cost estimate increased to £143 million (+62%) and the additional revenue requirement more than doubled to £1.4 million per annum.

“The Trust was advised to reassess the project in terms of its strategic fit, scale and scope of service needs, and range of feasible options, to allow the Department to consider value for money and affordability before the project could progress to the tender stage.

“The Department has provided feedback to the Trust on the business case and awaits a resubmission.

“The demand for new capital investment outstrips the draft budget settlement for both capital and associated revenue costs, and exceeds the capacity within estates teams.

“In these circumstances, the Department is undertaking a review to determine which projects will be progressed over the next few years.”

We’ll have more on the story as it develops.